The scheme was introduced to enhance the infrastructure for Cold Chain Logistics, Preservation and value addition facilities so that there will not be any break from the farm gate to the consumer in order to reduce post-harvest losses of horticulture and non-horticulture agri-produce. This will enable linking groups of producers to processors and market through a well-equipped supply chain and cold chain, thereby ensuring remunerative prices to farmers and year-round availability of food products to consumers.
Time schedule for completion and operationalization of project will be 20 months for projects in General Areas and 24 months in North East States, Himalayan States, ITDP Areas and Islands from the date of issue of the approval letter for the financial assistance.
|
Sl. No. |
Particulars |
Amount |
Time Period |
|
1 |
1st Installment |
25% |
8 months |
|
2 |
2nd Installment |
40% |
6 months |
|
3 |
3rd Installment |
35% |
6 months |
|
|
Total |
|
20 months |